Price from the cost database

Audience: Subcontractors · 4 min

Steps​

  1. Open the matching calculator on buildx.pro/costs with the job region set.
  2. Read the low/high range for your tier.
  3. Apply your production rate: crew cost per day divided by units per day.
  4. If your number lands outside the range, know why before submitting (access, difficulty, schedule compression).
  5. Submit itemized against the GC scope lines with exclusions stated.