Understanding estimates
Audience: Property owners · 5 min
Fixed vs allowance
Fixed lines are priced work. Allowances are budgets for undecided selections (fixtures, tile, appliances). A bid with large allowances is less certain than it looks. Ask for the allowance schedule and what happens when selections exceed it.
Change orders
Legitimate triggers: hidden conditions, owner-requested changes, code requirements discovered mid-job. Every change order should state scope delta, price delta, and schedule delta, signed before work starts.
Comparing bids
- Confirm identical scope across bidders.
- Compare line by line, not totals.
- Flag allowances that differ by more than 15 percent.
- Ask the cheapest bidder what they excluded.