Bidding from a budget spine
Audience: General contractors · 6 min
Prerequisites
- Takeoff quantities for the job
- Sub bids on identical scope lines
Steps
- Push takeoff quantities into the budget. Every line carries quantity, unit, and cost basis.
- Send subs the same scope lines. Bids arrive pre-structured for leveling.
- Level the bids: compare line by line, flag outliers, ask what the low bidder excluded.
- Set your bid from the leveled cost plus markup. The owner proposal inherits these lines.
- When scope changes, the change order references the same lines. No parallel books.
Done when
- Budget, sub bids, and owner proposal share one line structure